Tight running times for minimum $\ell_q$-norm load balancing: beyond exponential dependencies on $1/ε$

Lin Chen, Liangde Tao, José Verschae · DOI

In theoretical computer science, a common expectation for NP-hard optimization problems is the "exponential barrier." When seeking a $(1+\epsilon)$-approximation (a PTAS), researchers often anticipate a running time that grows exponentially with $1/\epsilon$, typically $2^{O(1/\epsilon)}$. However, recent work by Chen, Tao, and Verschae shatters this assumption for the classic problem of minimum $\ell_q$-norm load balancing. They demonstrate that a subexponential dependency on $1/\epsilon$ is achievable and prove that this new bound is essentially optimal.

The Problem: Identical Machine Scheduling

The study focuses on identical machine scheduling ($P || \sum C_i^q$). Given $n$ jobs with processing times $p_j$ and $m$ identical machines, the goal is to assign every job to a machine to minimize the sum of the $q$-th powers of the machine loads (for $q > 1$). This objective is equivalent to minimizing the $\ell_q$-norm of the machine loads.

While the problem is strongly NP-hard, it has long been known to admit a PTAS. However, for decades, the best algorithms exhibited a running time dependency on $1/\epsilon$ that was at least exponential (e.g., $2^{\Omega(1/\epsilon)}$). The authors investigated whether this exponential dependency is a fundamental limitation or if faster algorithms exist.

Algorithmic Innovation: The Upper Bound

Standard PTAS techniques for scheduling often involve rounding job sizes to powers of $(1+\epsilon)$, resulting in $O(1/\epsilon)$ job types and exponential state spaces in dynamic programming.

The authors' key insight involves using a coarser grouping of $(1+\sqrt{\epsilon})$. By applying a Taylor expansion to the objective function, they demonstrated that linear error terms cancel out when jobs are shifted between machines. This leaves only quadratic terms, allowing for a $(1+\epsilon)$ approximation while managing only $\tilde{O}(\sqrt{1/\epsilon})$ job types. This reduction directly leads to a subexponential running time of $2^{\tilde{O}(\sqrt{1/\epsilon})} + n^{O(1)}$.

Complexity Analysis: The Lower Bound

To establish the optimality of their algorithm, the authors performed a fine-grained reduction from a variant of 3SAT. This reduction encodes logic into job sizes such that only specific job combinations achieve a target objective value. To ensure the integrity of the reduction, they utilized advanced number-theoretic tools, specifically Salem-Spencer sets (sets containing no 3-term arithmetic progressions) and a novel construction termed linked unique sums. These ensure that job sizes possess unique additive properties, preventing "accidental" solutions.

The Complexity Landscape

A significant contribution of this work is the characterization of the problem's difficulty based on the relationship between the number of machines $m$ and the approximation parameter $\epsilon$.

As illustrated in the figure above, the complexity landscape is divided into three distinct regions:

  1. Small $m$ ($AL_1$): When $m < \sqrt{1/\epsilon}$, the problem is relatively easier, with a running time of $(1/\epsilon)^{O(m)}$.
  2. Intermediate $m$ ($AL_2$): This is the "hardest" region, where $\sqrt{1/\epsilon} \le m \le \frac{1}{\epsilon} \log^2 \frac{1}{\epsilon}$. Here, the subexponential bound $2^{\tilde{O}(\sqrt{1/\epsilon})}$ is tight.
  3. Large $m$ ($AL_3$): When $m > \frac{1}{\epsilon} \log^2 \frac{1}{\epsilon}$, the problem becomes solvable in time polynomial in $1/\epsilon$, specifically $(1/\epsilon)^{O(1)}$.

Key Results and Implications

  • New PTAS: The authors established an algorithm with a running time of $2^{\tilde{O}(\sqrt{1/\epsilon})} + n^{O(1)}$.
  • Tight Lower Bound: Under the Exponential Time Hypothesis (ETH), they proved that no PTAS can run in $2^{o((1/\epsilon)^{1/2-\delta})} + n^{O(1)}$ for any $\delta > 0$.
  • Breaking Makespan Symmetry: This result highlights a sharp contrast with the "minimum makespan" problem ($L_\infty$ norm), which has a known exponential lower bound of $2^{\Omega(1/\epsilon)}$. This proves that $\ell_q$ norms are fundamentally "easier" to approximate than the $L_\infty$ norm.

Future Directions

While this work provides a tight characterization for identical machines, several avenues remain open. Extending these subexponential bounds to related machines ($Q || \sum C_i^q$) or unrelated machines ($R || \sum C_i^q$) is a significant challenge. Additionally, the Taylor expansion technique might be applicable to other min-sum cost functions, potentially enabling subexponential PTASs for a broader class of combinatorial optimization problems.

Summary updated

Abstract

We consider a classical scheduling problem on $m$ identical machines. For an arbitrary constant $q&gt;1$, the aim is to assign jobs to machines such that $\sum_{i=1}^m C_i^q$ is minimized, where $C_i$ is the total processing time of jobs assigned to machine $i$. It is well known that this problem is strongly NP-hard. Under mild assumptions, the running time of an $(1+ε)$-approximation algorithm for a strongly NP-hard problem cannot be polynomial on $1/ε$, unless $\text{P}=\text{NP}$. For most problems in the literature, this translates into algorithms with running time at least as large as $2^{Ω(1/\varepsilon)}+n^{O(1)}$. For the natural scheduling problem above, we establish the existence of an algorithm which violates this threshold. More precisely, we design a PTAS that runs in $2^{\tilde{O}(\sqrt{1/ε})}+n^{O(1)}$ time. This result is in sharp contrast to the closely related minimum makespan variant, where an exponential lower bound is known under the exponential time hypothesis (ETH). We complement our result with an essentially matching lower bound on the running time, showing that our algorithm is best-possible under ETH. The lower bound proof exploits new number-theoretical constructions for variants of progression-free sets, which might be of independent interest. Furthermore, we provide a fine-grained characterization on the running time of a PTAS for this problem depending on the relation between $ε$ and the number of machines $m$. More precisely, our lower bound only holds when $m=Θ(\sqrt{1/ε})$. Better algorithms, that go beyond the lower bound, exist for other values of $m$. In particular, there even exists an algorithm with running time polynomial in $1/ε$ if we restrict ourselves to instances with $m=Ω(1/ε\log^21/ε)$.
BibTeX
@misc{chen2021tight,
  author = {Lin Chen and Liangde Tao and José Verschae},
  title = {{Tight running times for minimum $\textbackslash\{\}ell\_q$-norm load balancing: beyond exponential dependencies on $1/ε$}},
  year = {2021},
  eprint = {2107.06261},
  archivePrefix = {arXiv},
  url = {https://arxiv.org/abs/2107.06261},
}
Figure