Optimal Planning for Timed Partial Order Specifications

Kandai Watanabe, Georgios Fainekos, Bardh Hoxha, Morteza Lahijanian, Hideki Okamoto, Sriram Sankaranarayanan

Abstract

This paper presents a framework for planning optimal, time-sensitive task sequences for multi-robot systems. By modeling complex workflows as Timed Partial Orders (TPOs) and translating them into a variant of the Traveling Salesman Problem solved via Mixed Integer Linear Programming (MILP), the authors enable efficient planning for large-scale systems while ensuring formal robustness against real-world delays.

Problem Statement

In complex industrial workflows, such as aircraft turnaround operations, tasks are rarely independent. They involve intricate dependencies where some actions must occur sequentially (e.g., stairs must be placed before passengers deboard), while others can happen in parallel (e.g., refueling and catering). Furthermore, these tasks often have strict timing constraints, such as a requirement that catering begins at least 30 minutes after the aircraft arrives.

Figure 1: Aircraft turnaround tasks with complex dependencies.

Existing robotic planning methods often struggle to bridge the gap between high-level temporal requirements and low-level physical constraints, such as travel time between locations. This paper introduces a framework that uses Timed Partial Order (TPO) specifications to bridge this gap, offering an expressive yet computationally efficient solution.

Methodology

The proposed framework operates in three primary stages:

1. Modeling with Timed Partial Orders (TPOs)

Tasks are defined using TPOs, which are directed acyclic graphs where nodes represent events and edges represent precedence. TPOs incorporate "clocks" and "guards" to enforce specific time windows between events, allowing for a formal representation of complex workflows.

Figure 2: A Timed Partial Order (TPO) graph showing event sequences and timing constraints.

2. Translation to GTSP-TWPR

The robot's environment is modeled as a Deterministic Transition System (DTS). The combination of the TPO and the DTS is mapped into a Generalized Traveling Salesman Problem with Time-Windows and Precedence Relations (GTSP-TWPR). In this representation, nodes correspond to task locations, and edge costs represent the shortest travel times between them.

3. Optimization via MILP

The problem is formulated as a Mixed Integer Linear Program (MILP) with the objective of minimizing the total makespan (the time until the final task is completed). For multi-robot scenarios, the formulation allows for multiple "tours" starting from different initial positions. Interestingly, the authors found that adding TPO constraints actually speeds up the MILP solver by pruning the search space of "illegal" task sequences.

4. Robustness Analysis

To account for real-world uncertainties, a secondary Linear Program (LP) calculates a robustness bound ($\epsilon$). This value quantifies the maximum delay a plan can tolerate at any node or during travel before violating the original TPO constraints.

Key Results and Insights

The framework was evaluated using synthetic benchmarks and a realistic aircraft turnaround case study.

  • Scalability: The MILP solver successfully planned for 160 task nodes and 40 robots in approximately 182 ± 102 seconds.
  • Performance: In the aircraft turnaround study, the multi-robot plan achieved a makespan of 59 time units, significantly outperforming the single-robot makespan of over 150 units.
  • Physical Validation: The system was deployed on three Jackal UGV robots in a lab environment, demonstrating that the theoretical plans are viable for real-world hardware.
  • Comparison: The MILP approach outperformed general-purpose tools like Google's OR-Tools, as the specific timing constraints of TPOs often hinder the heuristics used by standard TSP solvers.

Conclusion and Future Work

This research provides a robust method for multi-robot task planning under complex temporal constraints. While current collision avoidance is handled as a post-processing step using robustness bounds to inject delays, future work aims to integrate proactive conflict resolution and explore dynamic task assignment in heterogeneous robot teams.

Summary updated

Abstract

This paper addresses the challenge of planning a sequence of tasks to be performed by multiple robots while minimizing the overall completion time subject to timing and precedence constraints. Our approach uses the Timed Partial Orders (TPO) model to specify these constraints. We translate this problem into a Traveling Salesman Problem (TSP) variant with timing and precedent constraints, and we solve it as a Mixed Integer Linear Programming (MILP) problem. Our contributions include a general planning framework for TPO specifications, a MILP formulation accommodating time windows and precedent constraints, its extension to multi-robot scenarios, and a method to quantify plan robustness. We demonstrate our framework on several case studies, including an aircraft turnaround task involving three Jackal robots, highlighting the approach’s potential applicability to important real-world problems. Our benchmark results show that our MILP method outperforms state-of-the-art open-source TSP solvers OR-Tools.
BibTeX
@inproceedings{watanabe2024optimal,
  author = {Kandai Watanabe and Georgios Fainekos and Bardh Hoxha and Morteza Lahijanian and Hideki Okamoto and Sriram Sankaranarayanan},
  title = {{Optimal Planning for Timed Partial Order Specifications}},
  booktitle = {IEEE International Conference on Robotics and Automation},
  year = {2024},
  url = {https://openreview.net/forum?id=tvPnEMKyC5},
}
Figure