Abstract
Charging infrastructure serves as the critical link between power and transportation networks. Determining optimal charging station siting is essential for the integrated planning of these systems. While previous research has typically optimized either station siting based on fixed travel patterns or fleet operations given fixed infrastructure, this paper introduces a linear programming framework that jointly optimizes both. By minimizing total costs—including vehicle and station procurement, energy consumption, and grid demand charges—the model determines the optimal number and type of charging plugs at each location alongside fleet routing. A case study in San Francisco reveals that small, energy-efficient EVs are the most cost-effective. Furthermore, optimal siting is more spatially distributed than current infrastructure, favoring high-power Level 2 AC stations. This joint approach reduces total costs, empty vehicle travel, and peak charging loads by approximately 10%.
Introduction: The Coupling of Infrastructure and Operations
As Electric Autonomous Mobility-on-Demand (E-AMoD) services emerge, the traditional approach to siting charging stations—placing them where human drivers currently park—becomes obsolete. Autonomous electric vehicles (AEVs) can drop off passengers and independently navigate to chargers or rebalance to areas of anticipated demand.
This paper argues that charging station siting and fleet operations are "intimately coupled." To achieve global efficiency, one must solve for infrastructure and routing simultaneously. We present a linear program (LP) that co-optimizes these variables to find the global optimum for cost and efficiency.
Methodology
The optimization framework uses an expanded state-space graph that tracks vehicle location, time, and State of Charge (SoC).
- Decision Variables: The model determines the number of charging plugs (Level 2 vs. DC Fast Charging) at each candidate zone and the optimal routing/charging schedule for the fleet.
- Cost Factors: The objective function includes fleet and station procurement, energy costs, maintenance, and demand charges (fees for peak power usage).
- Grid Management: The model incorporates "charge throttling," allowing the fleet to reduce charging rates during peak electricity price windows or to manage grid load.
Case Study: San Francisco
The framework was validated using 2019 travel demand data for San Francisco, comprising 2.89 million daily trips across 190 transportation analysis zones. We compared three vehicle models: the Tesla Model 3 Long Range, the Nissan Leaf S, and the Dacia Spring. Electricity pricing followed PG&E’s business EV schedules, which include time-of-use rates and subscription-based demand charges.
Key Insights
Efficiency Over Range
Counter-intuitively, the Dacia Spring—the smallest and shortest-range vehicle—proved most cost-effective. Its superior energy efficiency and lower procurement cost outweighed the operational burden of more frequent charging stops.
The Shift to Level 2 AC
The optimization favored high-power Level 2 AC stations (16.8 kW) over DC fast chargers. Because AEVs can manage their own schedules, they can utilize longer, cheaper charging sessions during off-peak hours, reducing the need for expensive fast-charging infrastructure.
Spatial Decentralization
Optimal AEV charging infrastructure is more spatially distributed than current human-centric siting. While current chargers cluster in commercial centers, the model suggests spreading them into residential and non-commercial zones where AEVs can "hide" and charge during midday lulls or overnight.
Key Results
- Cost Savings: Joint optimization achieved a 9.59% reduction in total ownership costs compared to a baseline siting scenario.
- Infrastructure Optimization: The model recommended a 64% reduction in installed DC fast-charging capacity, replaced by more distributed Level 2 AC plugs.
- Operational Efficiency: Empty-vehicle "rebalancing" travel decreased by 11.2%, as vehicles found optimal chargers closer to their routes.
- Grid Benefits: The peak charging load was reduced by 10.07%. Notably, the fleet successfully avoided all charging during the most expensive peak-pricing window (4 PM – 9 PM).
Conclusion
Jointly optimizing infrastructure and operations provides a significant advantage for AEV fleet planning, offering a roadmap for more efficient urban mobility and grid integration. Future work will aim to incorporate street-level traffic congestion, heterogeneous fleets, and Vehicle-to-Grid (V2G) capabilities.