TL;DR
This paper introduces a novel modeling concept for power flow calculations that unifies different voltage levels (MV and LV) into a single, coherent dataset. This approach simplifies strategic network planning by allowing for simultaneous analysis of transformers and lines across voltage levels, addressing the complexity introduced by the energy transition and new loads like EVs and heat pumps.
What Problem Does This Paper Address?
The ongoing energy transition, characterized by the increasing integration of new loads (e.g., EV charging, heat pumps) and distributed energy resources (DERs), is significantly increasing the complexity of strategic network planning. Traditionally, power flow analyses for dimensioning equipment like transformers and lines are performed separately for each voltage level (HV, MV, LV). This requires maintaining multiple, distinct datasets and applying different methods and simultaneity factors (SFs) for each level. This fragmented approach can lead to inconsistencies and potential under- or over-dimensioning of network components. The paper aims to bridge this gap by proposing a unified modeling concept that allows for a single power flow calculation across all relevant voltage levels, ensuring consistent and accurate dimensioning.
Methods
The core of the paper is the introduction of "Concept 2," a new modeling approach that contrasts with the traditional "Concept 1."
- Concept 1 (Traditional): Involves separate power flow calculations for each planning perspective (e.g., HV/MV transformers, MV lines, MV/LV transformers, LV lines). Each perspective uses its own data set and specific simultaneity factors (SFs), leading to different power flow results and potential inconsistencies.
- Concept 2 (Novel): Employs a holistic modeling approach where all network levels (e.g., MV and all underlying LV networks) are integrated into a single dataset. To account for the different SFs used in traditional planning perspectives, "compensation feed-ins" (CFs) are introduced. These CFs are modeled as active and reactive power injections at transformer nodes to balance the power differences arising from the varying SFs across different planning perspectives. This allows for a single power flow calculation to accurately represent the conditions across all modeled voltage levels.
The paper also discusses variations of Concept 1 (Concept 1a and 1b) to highlight the differences and advantages of Concept 2. Concept 1a uses fixed voltage band distributions, while Concept 1b attempts to incorporate some cross-voltage information.
Datasets
The study utilizes a comprehensive dataset representing an MV network with 53 underlying LV networks. This dataset includes parameters such as:
- Power rating of HV/MV transformers
- MV line length
- Number of MV feeders, distribution stations, customer stations, house connections, metering points, private charging points, public charging points, and electric heat pumps.
The data for new loads (charging points and heat pumps) is based on Germany-wide developments from the dena study "Integrated Energy Transition" (EL80 scenario) and distributed using a regionalization system.
Key Insights and Ideas
- Unified Modeling is Crucial: The traditional approach of separate analyses for each voltage level leads to inconsistencies and potential mis-dimensioning. A unified model is essential for accurate strategic planning.
- Simultaneity Factors (SFs) are Key, but Tricky: SFs are critical for realistic load assumptions, but their application across different planning perspectives (e.g., transformer vs. line) creates discrepancies.
- Compensation Feed-ins (CFs) Bridge the Gap: The novel CFs in Concept 2 effectively reconcile the different SFs used in traditional planning perspectives, enabling a single, coherent power flow calculation.
- Network Losses are Significantly Impacted: The holistic modeling in Concept 2, which includes losses from all network levels, leads to a more accurate representation of total network losses compared to traditional methods where some losses might be omitted.
- Overplanning Reduces Deviations: When networks are "overplanned" (reinforced to meet future demands and voltage limits), the differences between Concept 2 and traditional methods become less pronounced, suggesting that the proposed method is robust even in future scenarios.
Key Results
The paper presents a detailed comparison between Concept 2 and variations of Concept 1 (1a and 1b).
- Voltage Values: Concept 2 generally shows higher voltage drops across transformers compared to Concept 1a, due to the inclusion of LV line losses and more comprehensive modeling. However, when compared to Concept 1b (which uses voltage values from Concept 2), the differences are smaller, highlighting the impact of fixed voltage bands in Concept 1a.
- Equipment Loading: Loadings for HV/MV transformers are higher in Concept 2 due to increased network losses from underlying levels. MV line loadings are also generally higher in Concept 2, again attributed to the inclusion of LV line losses and MV/LV transformer losses. MV/LV transformer loadings show mixed results, influenced by higher voltage values and additional LV line losses.
- Network Losses: Concept 2 provides a more accurate representation of total network losses by considering all underlying network levels. Traditional methods (Concept 1a/1b) can underestimate losses due to unmodeled levels. However, Concept 2 might slightly overestimate losses by assuming simultaneous peak loading across all levels.
- Overplanning Impact: After overplanning the network, deviations in voltage drops and loadings between Concept 2 and Concept 1b were significantly reduced (e.g., voltage drop deviations for transformers reduced by up to 75%, loading deviations by up to 2.5 times).
Limitations and Future Work
- Network Loss Overestimation: Concept 2 may slightly overestimate network losses because it assumes simultaneous peak loading across all network levels. While CFs compensate for SF differences, they don't account for load-dependent network losses.
- Fuzziness of Network Modeling: The results are based on a specific MV network with specific cable types and transformer characteristics. Changes in these parameters could influence the observed deviations.
- Future Work: The authors suggest that the developed concept is a good opportunity to conduct realistic assessments of expansion measures and innovative technologies across all network levels. Further research could explore the impact of different cable types and transformer characteristics on the results. The paper also hints at the potential for using this concept for future supply tasks and mapping the effects of expansion measures.
Summary updated