The problem of scheduling preemptive jobs on parallel machines to minimize total completion time ($P|pmtn, r_j|\sum C_j$) is a cornerstone of scheduling theory. While the single-machine case is efficiently solvable using the Shortest Remaining Processing Time (SRPT) rule, the multi-machine variant has long been a subject of debate regarding its computational complexity. This paper identifies a critical flaw in a previously accepted 2007 proof of NP-hardness and provides a rigorous new reduction from 3-PARTITION to settle the question.
The Flaw in Previous Proofs
In 2007, it was claimed that $P|pmtn, r_j|\sum C_j$ is strongly NP-hard. However, the original proof relied on the assumption that certain jobs would necessarily be scheduled without preemption on a single machine. The authors of this note demonstrate that this assumption is invalid due to McNaughton’s algorithm, which allows jobs to be "sliced" and wrapped around machine boundaries without increasing the total completion time.
By providing a specific numerical counterexample involving 2 machines and 656 jobs, the authors show that the previous reduction fails to "force" the required structure, as jobs can be distributed across machines in ways the original proof did not account for.
A New Reduction from 3-PARTITION
To provide a valid proof of strong NP-hardness, the authors construct a sophisticated reduction from the 3-PARTITION problem. The reduction uses a highly structured schedule composed of four distinct job types designed to eliminate the flexibility afforded by preemption.
The construction relies on the following components:
- S-jobs (Staircase jobs): Released at specific intervals, these jobs force a "staircase" pattern on the machines, creating precise gaps that must be filled.
- X-jobs: These correspond to the integers in the 3-PARTITION instance. A valid partition exists if and only if these jobs fit perfectly into the gaps created by the S-jobs.
- F-jobs (Filler jobs): These ensure that no machine remains idle before the target deadline, acting as "grout" between the primary jobs.
- C-jobs (Cork jobs): These are unit-length jobs released at the very end of the schedule ($T$). They act as a "hard wall," ensuring that any delay in the preceding jobs results in a massive penalty to the total completion time.
Key Insights: The "Cork" Strategy and Delay
A central challenge in this proof was preventing preemption from "smearing" jobs across the schedule. The authors addressed this using the "Cork" strategy. By flooding the system with C-jobs at time $T$, they ensured that any job finishing even slightly after $T$ would push multiple C-jobs later, significantly increasing the objective function.
Furthermore, the authors simplified the analysis by focusing on total delay ($D_j = C_j - r_j - p_j$) rather than raw completion times. This mathematical shift allowed them to isolate the "extra" time jobs spent in the system due to machine contention, making the mapping to 3-PARTITION more transparent.
Conclusion
By establishing Theorem 1, this paper confirms that $P|pmtn, r_j|\sum C_j$ is indeed strongly NP-hard. This result clarifies a significant point in scheduling literature and underscores the subtle complexities introduced by preemption in multi-machine environments. While the problem's hardness is now firmly established, determining the tightest possible approximation ratios remains an open challenge for future research.