Status of the High Energy Beam Transport System for FAIR

F. Hagenbuck, Lars Bozyk, S. Damjanović, Andreas Krämer, Bruno Merk, C. Mühle, S. Ratschow, B. R. Schlei, P. Spiller, B. Walasek-Höhne, H. Welker, Christina WillJACOW 2015 · DOI

TL;DR

This paper provides an update on the High Energy Beam Transport (HEBT) system for the FAIR facility, detailing its current status, design adaptations, and procurement progress. Despite the introduction of new project phases like the Modularized Start Version (MSV), the HEBT system's overall layout remains robust and is being smoothly implemented, with key components already in procurement.

What Problem Does This Paper Address?

The paper addresses the ongoing development and implementation of the High Energy Beam Transport (HEBT) system, a critical infrastructure for the Facility for Antiproton and Ion Research (FAIR). The challenge lies in integrating new project phases, such as the Modularized Start Version (MSV), which involves adapting the existing HEBT layout and ensuring all components are designed, procured, and installed to meet the facility's stringent requirements. This includes managing complex beam line routing, ensuring safety, and coordinating procurement with international partners.

Methods

The authors describe the HEBT system's technical design and procurement status. Key methods include:

  • Adaptation of System Layout: Modifications to the beam line topology to accommodate new injection schemes and experimental areas, such as a direct connection from SIS18 to the CR and a revised transfer line to HESR.
  • 3D Modeling (CATIA): Development of a comprehensive 3D model of the entire HEBT system for detailed integration checks with buildings and infrastructure, and for deriving specifications for components.
  • FLUKA Simulations: Used for safety analysis, specifically to determine radiation levels and optimize the design of beam diffusors (safety beam plugs) for accidental beam deposition.
  • Procurement Strategy: A phased approach involving international in-kind contributions, GSI's direct procurement, and future FAIR tenders, with detailed contracts for magnets, vacuum chambers, and power converters.

Datasets

Not discussed in the paper.

Key Insights and Ideas

  • Robustness of Original Design: The HEBT system's original layout, established in 2008, has proven adaptable to new project phases like the MSV, minimizing the need for major structural changes.
  • Synergistic Component Reuse: The design for the transfer line from CR to HESR leverages components from the previous CR to RESR line, allowing for reuse by adapting dipole magnet bending angles and replacing vacuum chambers.
  • Integrated Safety Measures: The implementation of safety beam plugs (diffusors) through detailed FLUKA simulations highlights a proactive approach to radiation safety, ensuring acceptable levels even in case of malfunctions.
  • Complex Interconnections: The central transfer building (H0705A) presents a significant engineering challenge due to its intricate 3D beam line routing, requiring advanced assembly and alignment strategies.
  • International Collaboration in Procurement: A substantial portion of the HEBT system's components are being procured through international partnerships, demonstrating a collaborative approach to building FAIR.

Key Results

  • Adaptations Implemented: A new direct connection from SIS18 to the CR has been successfully integrated. The transfer line to HESR has been rerouted via the CR as a mitigation measure for the delayed RESR construction.
  • Procurement Status: As of April 2014, 62% of the HEBT system is assigned to international partners, 20% to GSI, and 18% is yet to be assigned or procured.
  • Magnet Production: Contracts for dipole and quadrupole magnets are in progress with Russian institutes (NIIEFA, BINP), with pre-series dipole magnets already under production.
  • Power Converter Contracts: Contracts for quadrupole and steering magnet power converters are being established with Indian partners (Bose Institute, ECIL), with deliveries scheduled between 2015 and 2018.
  • Beam Diagnostics: Detailed specifications for standard diagnostic vacuum chambers have been provided to the Indian shareholder Bose Institute, and contracts for BPM pre-amplifiers and data acquisition systems are in place.

Limitations and Future Work

  • Delayed RESR Construction: The delay in the RESR construction necessitates a temporary rerouting of the transfer line to HESR, which will be replaced by a new line once RESR is operational.
  • Procurement Timeline: While significant progress has been made, the delivery of all components, particularly for the third batch of magnets and vacuum chambers, is expected to extend to the end of 2017.
  • Future Work: The paper mentions ongoing work on specifications for the support structure and transportation units in building H0705A, as well as the negotiation of contracts for the third batch of magnets and vacuum chambers. The continued integration and installation of components are implied as the next steps.

Summary updated

Abstract

The overall layout of the High Energy Beam Transport (HEBT) System of the Facility for Antiproton and Ion Research (FAIR)* did not change since its last presentation in 2008**. All necessitated adaptions as for example due to the introduction of the Modularized Start Version (MSV, module 0-3) of FAIR*** could be smoothly implemented. In the meanwhile the HEBT system is in its realisation phase with the procurement of its main components in progress. In the following adaptions of the system layout not yet covered in ** are summarized and an overview of the technical system design and procurement status are presented.
BibTeX
@inproceedings{hagenbuck2015status,
  author = {F. Hagenbuck and Lars Bozyk and S. Damjanović and Andreas Krämer and Bruno Merk and C. Mühle and S. Ratschow and B. R. Schlei and P. Spiller and B. Walasek-Höhne and H. Welker and Christina Will},
  title = {{Status of the High Energy Beam Transport System for FAIR}},
  booktitle = {JACOW},
  year = {2015},
  doi = {10.18429/jacow-ipac2015-thpf012},
}
Figure