Scheduler Modeling of Distributed Energy Resources for Providing Ancillary Services

Xiaofei Wang, Renewable Power Office. Solar Energy Technologies Office Usdoe Office of Energy Efficiency and Renewable Energy (eere), Jing Wang, Joshua Comden, Cindy Buck, Nicholas Pollman, Ben Sigrin2026 · DOI

Abstract

Distribution energy resources (DERs) have been integral components of modern power systems, and their capability to provide grid services has been widely studied. To promote the deployment of these resources in providing grid services in real-world utility operations, this paper proposes a day-ahead scheduler model for a distribution system connected DER plant. A certain amount of generation capacity of this DER plant is reserved for frequency services, and some ancillary services for the distribution system—including peak load reduction, voltage regulation, and power factor control—are integrated into the model. The model is tested on a real-world distribution system. From the simulation results, the energy and reserve schedule of the solar photovoltaic (PV) unit and battery energy storage system (BESS) can be determined, and voltage and power factor are well maintained. Additionally, in order to demonstrate the specific characteristics of the co-located and hybrid operation modes for the PV and BESS, these two modes are analyzed both theoretically and through real-time simulation. Simulation results show that most of PV's variability is transferred to the net power in the co-located mode, whereas it is transferred to the BESS in the hybrid mode. This proposed scheduler model and the comparison of co-located and hybrid modes can provide practical guidance for the applications of DER plant in the real-world utility.

Introduction

As the global energy landscape transitions toward cleaner sources, Distributed Energy Resources (DERs), such as solar photovoltaics (PV) and Battery Energy Storage Systems (BESS), are evolving from passive additions to the backbone of modern power systems. However, managing these resources to maintain grid stability while maximizing economic value remains a significant challenge for utility operators. This study, conducted by researchers at the National Renewable Energy Laboratory (NREL) in collaboration with the Public Service Company of New Mexico (PNM) and GridBeyond, introduces a sophisticated look-ahead scheduler designed to optimize DER operations for ancillary services.

Problem Statement

Traditional power system models often assume a balanced grid where the three phases of electricity are roughly equal. In practice, distribution systems are frequently unbalanced, complicating modeling and control. Furthermore, the inherent variability of solar generation introduces volatility that can stress grid infrastructure. To achieve utility-scale integration, DERs must provide more than just raw power; they must offer ancillary services—such as voltage regulation and peak load reduction—to act as "shock absorbers" for the grid. The challenge lies in creating a scheduler that can co-optimize energy sales with these reserve requirements in a complex, three-phase environment.

Methodology

The researchers developed a Three-phase Scheduler Model that minimizes electricity purchase costs while adhering to strict physical and operational constraints. Key features of the methodology include:

  • Look-ahead Co-optimization: The model utilizes day-ahead and real-time forecasts to schedule energy and reserves simultaneously.
  • Three-phase Modeling: Unlike simplified synthetic benchmarks, this model accounts for the unbalanced nature of real-world distribution feeders.
  • Integrated Ancillary Services: The scheduler explicitly manages peak load reduction, voltage regulation, and power factor control.
The utility test system used for validation, featuring a distribution feeder connected to PV and BESS units at the point of interconnection.

The model was validated using a practical utility test system provided by PNM, utilizing hourly day-ahead and 5-minute real-time forecasts for solar generation and load demand.

Key Insights and Results

Operational Modes: Co-located vs. Hybrid

A critical finding of the study is the distinction between operation modes. In a co-located setup, PV and BESS operate independently, passing solar volatility directly to the grid. In a hybrid mode, the BESS acts as a primary buffer, absorbing solar fluctuations before they reach the wider network. This internalization of variability leads to a significantly smoother net power profile at the point of interconnection.

Grid Stability and Voltage Regulation

By integrating voltage constraints directly into the optimization objective, the scheduler ensures that the voltage profile across all buses remains within the tight range of 0.95 to 1.05 per-unit (p.u.), even during periods of high solar fluctuation.

Simulation results demonstrating that the scheduler maintains system voltage within the required 0.95 to 1.05 p.u. bounds throughout the 24-hour cycle.

Peak Load Reduction

The BESS successfully performed "time-shifting," storing excess solar energy during peak production hours and discharging it when PV generation decreased. This effectively reduced the peak demand on the substation, demonstrating the system's ability to provide tangible benefits to utility operations.

Conclusion and Future Work

This scheduler model provides a practical framework for deploying DERs in real-world utility environments. While the high-fidelity simulations are promising, future work will focus on integrating the forecaster, scheduler, and dispatcher into a unified control framework. Subsequent phases will involve Hardware-in-the-loop (HIL) testing to verify performance with physical hardware before field deployment, alongside studies on the scalability of the scheduler across larger, multi-feeder networks.

Summary updated

Abstract

Distribution energy resources (DERs) have been integral components of modern power systems, and their capability to provide grid services has been widely studied. To promote the deployment of these resources in providing grid services in real-world utility operations, this paper proposes a day-ahead scheduler model for a distribution system connected DER plant. A certain amount of generation capacity of this DER plant is reserved for frequency services, and some ancillary services for the distribution system-including peak load reduction, voltage regulation, and power factor control-are integrated into the model. The model is tested on a real-world distribution system. From the simulation results, the energy and reserve schedule of the solar photovoltaic (PV) unit and battery energy storage system (BESS) can be determined, and voltage and power factor are well maintained. Additionally, in order to demonstrate the specific characteristics of the co-located and hybrid operation modes for the PV and BESS, these two modes are analyzed both theoretically and through real-time simulation. Simulation results show that most of PV's variability is transferred to the net power in the co-located mode, whereas it is transferred to the BESS in the hybrid mode. This proposed scheduler model and the comparison of co-located and hybrid modes can provide practical guidance for the applications of DER plant in the real-world utility.
BibTeX
@misc{wang2026scheduler,
  author = {Xiaofei Wang and Renewable Power Office. Solar Energy Technologies Office USDOE Office of Energy Efficiency and Renewable Energy (EERE) and Jing Wang and Joshua Comden and Cindy Buck and Nicholas Pollman and Ben Sigrin},
  title = {{Scheduler Modeling of Distributed Energy Resources for Providing Ancillary Services}},
  year = {2026},
  doi = {10.2172/3019719},
}
Figure