Modular Structure Construction Progress Scenario: A Case Study of an Emergency Hospital to Address the COVID-19 Pandemic

Lingkun Chen, Chencheng Zhai, Lu Wang, Xiaolun Hu, Xiaoming HuangSustainability 2022 · DOI

TL;DR

This paper details the rapid construction of an emergency hospital for COVID-19 patients using modular integrated construction (MiC) and Building Information Modeling (BIM). It highlights how these technologies, combined with intelligent systems, enabled swift design, fabrication, and assembly, offering a scalable solution for future emergency infrastructure needs.

What Problem Does This Paper Address?

The COVID-19 pandemic created an urgent need for rapidly deployable healthcare facilities. Traditional construction methods are often too slow and resource-intensive to meet such immediate demands. This paper addresses the challenge of quickly constructing specialized emergency hospitals by exploring the application of modular integrated construction (MiC) and advanced digital technologies like Building Information Modeling (BIM) and intelligent systems. The goal was to overcome the limitations of conventional construction in terms of speed, efficiency, and adaptability for crisis situations.

Methods

The study employs a multi-faceted approach centered around Modular Integrated Construction (MiC) and Building Information Modeling (BIM).

  • Modular Design and Assembly: The core methodology involved designing and fabricating building components (modules) off-site in a controlled factory environment. These modules were then transported and assembled on-site, significantly reducing construction time and improving quality control. The paper specifically focuses on Modular Steel Buildings (MSBs).
  • Building Information Modeling (BIM): BIM was used extensively throughout the project. It facilitated:
  • Design Evaluation and Comparison: Assessing different construction plans and optimizing the design.
  • Detailed Design: Developing combined sections and connection node plans for the assembled steel structures.
  • Simulation and Coordination: Creating a digital twin to simulate construction processes, identify potential clashes (e.g., between pipes and structural elements), and ensure seamless integration of various building systems.
  • Data Exchange: Enabling efficient information flow between different disciplines and stakeholders.
  • Intelligent Systems Integration: The project incorporated an intelligent operation and maintenance management platform utilizing 5G, AI, IoT, cloud computing, and big data. This aimed to enhance real-time monitoring, predictive analytics, and overall facility management.
  • Standardized and Scalable Design: The hospital layout adopted a "fishbone" configuration, a design inherited from previous emergency responses (like SARS), known for its scalability and ability to manage patient flow and prevent cross-contamination.

Datasets

Not discussed in the paper. The study focuses on a specific case study (Vulcan Mountain Hospital/Huoshen Mountain Hospital) and its design and construction process, rather than relying on pre-existing datasets for training or evaluation.

Key Insights and Ideas

  • Information and Data Interaction is Key: The paper strongly emphasizes that the seamless flow of information and data between design, fabrication, and on-site assembly is the critical factor for achieving rapid construction.
  • BIM as a Central Hub: BIM acts as the unifying platform, enabling digital simulation, clash detection, and efficient coordination, which are crucial for complex projects with tight deadlines.
  • Modularization for Speed and Quality: MiC, particularly with steel modules, allows for parallel processing (factory fabrication and site preparation) and a higher degree of standardization, leading to faster construction and improved quality control compared to traditional methods.
  • Scalability for Future Crises: The "fishbone" design, proven effective in past outbreaks, offers inherent scalability, allowing for rapid expansion of capacity as an epidemic progresses.
  • Integration of Intelligent Technologies: The inclusion of 5G, AI, and IoT is presented not just as an add-on but as a fundamental component for creating a "smart" emergency hospital capable of efficient operation and maintenance.

Key Results

  • Rapid Construction: The emergency hospital was completed in an exceptionally short timeframe, with specific construction phases (e.g., foundation, module installation) being significantly accelerated. For instance, the Vulcan Mountain Hospital scheme reportedly saved 18 days through BIM implementation.
  • Efficient Design and Coordination: BIM facilitated the evaluation and optimization of construction solutions, leading to a more streamlined design and assembly process.
  • Enhanced Infection Control: The "three zones and two channels" design, coupled with modular sealing devices and anti-seepage technology, effectively addressed infection prevention and control requirements.
  • Scalable and Adaptable Infrastructure: The modular approach allowed for the creation of a functional emergency hospital that could be rapidly deployed and potentially expanded.

Limitations and Future Work

  • Limitations:
    • EMT Project Context: The paper acknowledges that the Vulcan Mountain Hospital/Huoshen Mountain Hospital was an Emergency Medical Treatment (EMT) project. This means its design and construction were optimized for immediate crisis response rather than long-term durability or traditional hospital standards. The remarkable timing and global testimony are noted, but the experience might be "somewhat important" for long-term applications.
  • Standardization Gaps: The paper points out that emergency buildings still lack comprehensive standardized series of standards, making it challenging for enterprises to reference.
  • Winter Construction Challenges: The project faced difficulties due to winter construction conditions, requiring special measures for concrete pouring and ground hardening.
  • Future Work:
    • Further Integration of Digital Tools: The paper suggests that digital tools and technologies (DTT) are underutilized in the prefabricated transportation phase of MiC, indicating potential for further optimization.
  • Blockchain and Other DTTs: The study highlights the significant potential for blockchain and other integrated DTTs in MiC projects.
  • Lifecycle Performance: The need for more research into interconnected building systems to improve lifecycle performance through digital twins is mentioned.
  • Developing Standards: The authors implicitly suggest the need for developing more standardized guidelines for emergency medical facilities, drawing from experiences like this project.

Summary updated

Abstract

Recently, emergency structures have been in the spotlight because of the coronavirus disease (COVID-19) pandemic. This research examines the use of modular integrated construction (MiC) in developing an emergency hospital for individuals with novel coronavirus-infected pneumonia (NCIP). The whole process of building is based on the modular design and assembly idea. The primary structure was constructed using the modular steel buildings (MSBs) concept to suit emergency structures’ functional qualities and quick construction needs. An intelligent operation and maintenance management platform was built utilizing 5G, AI, IoT (IoT), cloud, big data, an d other technologies. A BIM model was created to evaluate and compare the construction plan, develop the combined section and connection node plan, and complete the detailed design of assembled steel structures. On-site modularization of fundamental structural components and accessories is utilized in a flowing operating mode, where the housing and supporting installation are closely coordinated. The research results show that information and data interaction is the key to speedy building design and construction, with digital simulation in one stage and on-site assembly in a crammed way. The study findings may be used to build comparable structures faster, utilizing modular building techniques.
BibTeX
@inproceedings{chen2022modular,
  author = {Lingkun Chen and Chencheng Zhai and Lu Wang and Xiaolun Hu and Xiaoming Huang},
  title = {{Modular Structure Construction Progress Scenario: A Case Study of an Emergency Hospital to Address the COVID-19 Pandemic}},
  booktitle = {Sustainability},
  year = {2022},
  doi = {10.3390/su141811243},
}
Figure