This paper introduces a novel methodology for estimating software project working time by leveraging a database of past projects and their use case complexities. By analyzing standardized use cases and tracking project progress, the authors aim to provide more accurate and less human-dependent estimations, achieving a 10% improvement over traditional ad-hoc methods.
What Problem Does This Paper Address?
Accurately estimating the time and effort required for software development projects is a notoriously difficult but crucial task for project managers. Traditional methods often rely heavily on the experience of individual developers, making estimations subjective and prone to significant inaccuracies. This reliance on human judgment can lead to projects running over budget and schedule. The authors identify a need for a more structured, data-driven approach that can be applied consistently within a specific company, reducing the dependency on individual expertise and improving the reliability of project timelines.
Methods
The proposed methodology consists of two main processes: "Filling of the database" and "Estimation of a new project."
1. Filling the Database: * Method for finding progress: This involves tracking the progress of five main project activities: Consultation, Analysis, Programming, Testing, and Implementation. Project timelines are normalized by splitting them into a fixed number of segments (default 10). Progress within each segment is then evaluated by either counting all days or only days with actual work performed. The effort for each activity within each segment is recorded. * Method for determining the difficulty of a Use Case: This method assesses the complexity of use cases based on several factors: * Basic Complexity: Number of rows in the use case realization (categorized as Easy, Medium, Hard). * Extended Complexity: Number of words and paragraphs in the use case realization (also categorized as Easy, Medium, Hard). * Overall Difficulty: A weighted combination of word, row, and paragraph difficulties, with word difficulty carrying the highest weight.
2. Estimation of a New Project: * Once a new project's analysis (including use cases) is complete, its use cases are evaluated using the "Method for determining the difficulty of a Use Case." * The system then searches the database for past projects with similar use case difficulties (within a +/- 2 tolerance). * The average progress of these similar past projects is used to estimate the working time effort for the new project.
Datasets
The methodology was tested on 20 past projects from a specific company. Fifteen of these projects were used to fill the database, and five were used as new projects for evaluation. The paper does not introduce a new benchmark dataset but rather utilizes the company's internal project data.
Key Insights and Ideas
- Standardization is Key: The use of standardized use cases within a company is a critical enabler for this methodology, allowing for meaningful comparisons across projects.
- Multi-faceted Use Case Difficulty: Moving beyond simple metrics like lines of code, the methodology's strength lies in its multi-dimensional approach to use case difficulty, incorporating rows, words, and paragraphs, with a weighted emphasis on words.
- Normalization for Comparison: The technique of normalizing project timelines into a fixed number of segments is essential for comparing projects of vastly different durations.
- Data-Driven Estimation: The core idea is to shift from subjective, experience-based estimations to objective, data-driven estimations derived from historical project performance.
Key Results
The methodology was tested on 20 past projects. After filling the database with 15 projects, 5 new projects were estimated. The predicted project progress (effort per activity) was compared to the actual historical data for these 5 projects. The authors report an average difference of approximately 30% between the predicted and actual progress. They highlight that this represents a 10% improvement over the company's previous ad-hoc human-based estimations, which had an inaccuracy of around 40%.
Limitations and Future Work
- 30% Inaccuracy: While an improvement, the authors acknowledge that a 30% inaccuracy is still significant and indicates room for further improvement.
- Company-Specific: The methodology is explicitly stated to be based on the standards of a particular company and may not be directly generalizable without adaptation.
- Future Work:
- Neuron Nets: The authors plan to explore the use of neural networks to automatically identify groups of similar projects, potentially improving the accuracy of similarity matching.
- Customer Influence: Investigating parameters that describe the influence of the customer on project outcomes.
- More Parameters: Exploring the use of additional parameters to describe use cases for more refined estimations.
- Early Analysis: The current methodology estimates after the first steps of analysis (use cases are finished). Future work might consider how to incorporate the effort of this initial analysis phase into the overall estimation.
- Generalizability: The ultimate goal is to develop methods that can be used across multiple companies, leading to more accurate results.