TL;DR
This paper introduces a novel dual-level scheduling framework for prefabrication projects in construction. It tackles the challenge of frequent resource transfers and disconnected planning by integrating resource allocation and activity scheduling, leading to more robust schedules and better synchronization across management functions.
What Problem Does This Paper Address?
Construction prefabrication projects, especially those involving large, heavy components, often operate in a multi-project environment with limited space. This leads to a critical issue: frequent resource transfers between projects are not only inefficient but also disrupt workflow, reduce productivity, and increase management complexity. Existing scheduling methods often treat projects independently or create overly complex "super-projects," failing to adequately address these inter-project dependencies. Furthermore, there's a disconnect between high-level project planning and on-the-ground operational realities, meaning changes like material logistics delays aren't effectively incorporated into schedules, impacting cost and timelines.
Methods
The core of this research is a dual-level resource-constrained multi-project scheduling framework. This framework operates on two interconnected levels:
- Upper Level (Resource Allocation): This level focuses on allocating resources to entire projects (or "macro-activities" representing aggregated project phases). It aims to balance resource demands across multiple concurrent projects, effectively resolving resource conflicts and determining project-level milestones.
- Lower Level (Activity Scheduling): This level takes the resource allocations and milestones from the upper level and schedules individual activities within each project. It incorporates project-specific constraints like material logistics and design readiness.
The framework utilizes constraint programming for optimization at both levels. A key innovation is the introduction of macro-activities, which aggregate detailed tasks to simplify resource allocation and reduce inter-project transfers. The paper also defines a new metric, "resource use robustness," to quantitatively measure the impact of inter-project resource dependencies on schedule stability.
Datasets
The paper utilizes data from:
- Two literature case studies: These are adapted from previous research to illustrate the framework's capabilities.
- Two actual case studies: These involve bridge girder fabrication projects from a partner company in Edmonton, Canada. This real-world data is crucial for demonstrating the framework's practical applicability.
Key Insights and Ideas
- Decomposing complexity: The dual-level approach effectively breaks down the complex multi-project scheduling problem into manageable upper and lower levels, mirroring real-world project management structures.
- Macro-activities as a bridge: Aggregating detailed activities into macro-activities is a clever way to simplify resource allocation at the project level while still allowing for detailed scheduling at the operational level.
- Quantifying schedule robustness: The "resource use robustness" indicator provides a much-needed metric to assess how susceptible a schedule is to disruptions caused by shared resources, moving beyond traditional cost and duration metrics.
- Bridging planning and execution: By linking upper-level resource allocation with lower-level activity scheduling, the framework aims to align project planning with operational realities, making schedules more realistic and adaptable.
Key Results
The research demonstrates that the proposed dual-level framework:
- Reduces inter-project resource transfers: Case studies showed a significant reduction in resource transfers compared to traditional single-project methods, leading to higher resource use robustness (e.g., 90.5% for the proposed method vs. 34.3% for a single-project method in one scenario).
- Improves schedule synchronization: The framework enables the creation of interconnected program, project, and operation schedules, facilitating better communication and decision-making.
- Analyzes material logistics impact: The lower-level model can effectively simulate the impact of material delivery uncertainties on project cost and schedule, providing crucial decision support for practitioners. For instance, it can identify budget-constrained delivery time windows.
- Achieves practical feasibility: The framework was validated through real-world bridge girder fabrication projects, with expert confirmation of its practical applicability and potential for cost and time savings.
Limitations and Future Work
- Deterministic framework: The current research primarily uses a deterministic framework. Future work could extend this by incorporating stochastic models to account for uncertainties like rework, change orders, and variations in activity durations and resource requirements.
- Dynamic feedback loop: The authors suggest developing a closed feedback loop where dynamic changes at the lower level (operational progress) continuously inform and update decisions at the upper level (resource allocation), leading to more dynamic project control.
- Resource transfer costs: Further research could explore quantifying setup costs, material handling costs, and labor productivity losses due to unlearning curves to better integrate resource transfer costs into the optimization objective.
- Scalability: While demonstrated on projects with over 2,000 activities, the scalability of the models for even larger and more complex project networks warrants further investigation through systematic simulation tests.
- Additional constraints: The framework could be enhanced by incorporating more scheduling constraints, such as engineering drawing availability and limited workspace, to analyze their impact on project schedule performance.