Critical Path-Based Iterative Heuristic for Workflow Scheduling in Utility and Cloud Computing

Zhicheng Cai, Xiaoping Li, Jatinder N. D. GuptaICSOC 2013

In the world of cloud and utility computing, time is literally money. When you run a complex sequence of tasks—a "workflow"—you are constantly balancing two opposing forces: the need to finish before a deadline and the desire to minimize the cost of renting virtual machines (VMs).

A new paper by Zhicheng Cai and colleagues introduces a clever way to navigate this trade-off using an iterative heuristic that focuses on the "critical path" of a project.

TL;DR

The researchers developed the Critical Path-based Iterative (CPI) heuristic to minimize the cost of running large-scale cloud workflows under strict deadlines. By iteratively identifying and optimizing complete critical paths using dynamic programming, CPI achieves up to a 20.7% cost reduction compared to previous state-of-the-art algorithms.

What Problem Does This Paper Address?

Modern applications—like weather forecasting or big data analysis—are often modeled as Directed Acyclic Graphs (DAGs). In these graphs, nodes are tasks and arrows represent dependencies (Task B can't start until Task A finishes).

In a "pay-as-you-go" cloud environment, you can choose between different VM types: a high-performance instance finishes a task quickly but costs more, while a cheaper instance takes longer. The challenge is to assign the right "service" to each task so that the entire workflow finishes by a specific deadline ($D$) at the lowest possible total rental cost. Because this is an NP-hard problem, finding the perfect solution for a workflow with thousands of tasks is computationally impossible in a reasonable timeframe.

Methods

The authors propose the CPI (Critical Path-based Iterative) heuristic. Its approach differs from previous methods in three key ways:

  1. Complete vs. Partial Paths: Earlier algorithms (like PCP) only looked at "partial" critical paths. CPI looks at the complete critical path from the start of the workflow to the end.
  2. Iterative Refinement: The algorithm starts by assigning all tasks to their cheapest (and slowest) services. It then identifies the critical path—the longest chain of tasks that determines the total duration. If this path exceeds the deadline, CPI optimizes it. This process repeats, finding new critical paths as task durations change, until the deadline is met.
  3. MDP Relaxation: To make the optimization manageable, the authors treat the critical path as a Multi-stage Decision Process (MDP). They use a Dynamic Programming (DP) based Pareto method to find the best balance of cost and time for the tasks on that specific path.

Datasets

The researchers evaluated their algorithm using 1,350 randomly generated problem instances. These benchmarks were designed to test various conditions:

  • Scale: Workflow sizes ranging from 200 to 1,000 activities.
  • Service Variety: 2 to 30 different service options per task.
  • Network Complexity: Different "Order Strengths" (how interconnected the tasks are).
  • Cost Functions: Testing concave, convex, and hybrid relationships between task duration and cost.
  • Deadline Tightness: Varying how much "slack" time is available.

Key Insights and Ideas

  • The "Moving Target" of Criticality: The most insightful part of the paper is the realization that optimizing one path often makes a different path "critical." By iterating and re-calculating the complete path every time, CPI avoids the local-optima traps that catch simpler heuristics.
  • Efficiency through Relaxation: By temporarily "deleting" tasks and constraints not on the current critical path (the MDP relaxation), the authors can use powerful Dynamic Programming techniques that would otherwise be too slow for the entire graph.
  • Robustness over Exactness: While exact solvers like CPLEX work well for tiny problems, CPI proved more "robust" for large-scale workflows, providing high-quality solutions in under a minute where exact solvers struggled with the complexity.

Key Results

  • Cost Savings: CPI consistently outperformed existing heuristics (DET and PCP). For large workflows (1,000 tasks), CPI achieved a 20.7% decrease in average normalized resource renting costs compared to the PCP algorithm.
  • Performance vs. Exact Solvers: On complex network structures, CPI actually found better (cheaper) solutions than the commercial solver CPLEX when given the same amount of computation time.
  • Scalability: Even for the largest instances (1,000 nodes), the algorithm finished in under 42 seconds, making it practical for real-world cloud scheduling.

Limitations and Future Work

While CPI is highly effective, the authors note a few areas for improvement:

  • Computation Time: While fast (< 1 min), CPI is still more computationally intensive than "one-pass" heuristics like DET.
  • Static vs. Dynamic: The current model assumes task durations and costs are known upfront. In real cloud environments, performance jitter and "spot price" fluctuations could impact the schedule.
  • Future Directions: The authors suggest exploring new decomposition methods and investigating mathematical "bounds" to better understand how close their heuristic gets to the absolute theoretical minimum cost.

Summary updated

BibTeX
@inproceedings{cai2013critical,
  author = {Zhicheng Cai and Xiaoping Li and Jatinder N. D. Gupta},
  title = {{Critical Path-Based Iterative Heuristic for Workflow Scheduling in Utility and Cloud Computing}},
  booktitle = {ICSOC},
  year = {2013},
  doi = {10.1007/978-3-642-45005-1\_15},
}
Figure