Analysis of the Transmission of Project Duration and Cost Impacts Based on the GERT Network Technique

Zhiyong Li, Xiangtian Nie, Bo Wang, Tianyu FanSymmetry 2019

TL;DR

This paper introduces a novel GERT network model to analyze how project duration and cost impacts propagate through different project phases. By integrating risk transmission theory with GERT, the authors provide a framework to quantify and predict these cascading effects, offering a new tool for better project cost and schedule control.

What Problem Does This Paper Address?

Managing large-scale engineering projects, particularly hydraulic ones, is fraught with risks. These risks don't exist in isolation; they can originate in one phase and cascade, impacting the duration and cost of subsequent phases. This phenomenon, known as risk transmission, is complex because impacts can be additive, mutated, and even create feedback loops where downstream issues affect upstream ones. While existing research has explored risk transmission and project duration control, a significant gap exists in understanding and quantifying the interactive influence of both duration and cost impacts, especially when considering duration compensation mechanisms. This paper aims to fill that gap by developing a model that captures these dynamic interactions.

Methods

The core of this paper is the development of a GERT (Graphic Evaluation and Review Technique) network model. GERT is chosen for its ability to handle probabilistic events and complex network structures. The authors adapt GERT by:

  • Defining Equivalent Parameters: They establish specific parameters within the GERT model to represent duration gain-loss and cost loss transmission between project tasks (nodes). Duration compensation from downstream to upstream is also modeled.
  • Modeling Network Structures: The model accounts for three fundamental network structures: serial (tasks in sequence), parallel (multiple paths for a task), and hybrid (structures with loops or feedback).
  • Moment Generating Functions (MGFs): The paper leverages MGFs to mathematically describe the probabilistic distributions of duration and cost impacts. This allows for the calculation of expected values and variances.
  • Transfer Functions: Characteristic transfer functions are derived for each branch of the GERT network, representing the probabilistic transmission of duration and cost impacts.
  • Mason's Gain Formula: This signal flow graph technique is employed to simplify complex GERT networks into a single equivalent transfer function, enabling the calculation of overall project duration and cost transmission.
  • Multi-Risk Factor Analysis: The model is extended to handle multiple independent risk factors, using linear combinations and MGFs to derive a unified transfer function for activities with several risks.

Datasets

Not discussed in the paper. The paper presents a case study with hypothetical parameters for a water supply project.

Key Insights and Ideas

  • Interconnectedness of Duration and Cost: The most significant insight is the explicit modeling of how duration and cost impacts are not independent but rather transmit and influence each other across project phases.
  • Duration Compensation as a Key Factor: The paper highlights the importance of duration compensation, where downstream phases can mitigate upstream delays. This feedback mechanism is crucial for a realistic model.
  • GERT as a Powerful Tool: The study demonstrates the versatility of GERT in modeling complex, probabilistic systems like project risk transmission, moving beyond simpler PERT/CPM methods.
  • Quantifying Cascading Effects: By using MGFs and transfer functions, the paper provides a quantitative method to predict the cumulative impact of risks on project duration and cost, moving from qualitative risk assessment to quantitative prediction.

Key Results

The paper successfully constructs and solves a GERT network model for a five-phase water supply project. Through a case analysis using hypothetical data, they demonstrate the model's ability to:

  • Calculate the equivalent probability of duration gain-loss and cost loss transmission from the project's identification phase (node 1) to its transfer phase (node 5). For the case study, this probability was found to be 0.8560.
  • Determine the expected value of duration gain-loss transmission as 78.23 (units not specified, likely days) and cost loss transmission as 132.52 (units not specified, likely in ten thousand Yuan).
  • Quantify the variance of duration gain-loss transmission as 62.57 and cost loss transmission as 103.28, indicating the degree of uncertainty in these impacts.

The paper also provides detailed tables of activity parameters, moment generating functions, and transfer functions, showcasing the practical application of the developed methodology.

Limitations and Future Work

The authors acknowledge that their study focuses on the transmission of duration and cost impacts between project phases and does not consider feedback effects between different projects. The case study uses hypothetical parameters, suggesting that real-world data would be necessary for validation.

Future work could involve:

  • Extending the model to incorporate inter-project feedback.
  • Validating the model with real-world project data.
  • Exploring more complex risk interaction models beyond linear correlations.
  • Investigating the application of this methodology to other types of engineering projects.

Summary updated

BibTeX
@article{li2019analysis,
  author = {Zhiyong Li and Xiangtian Nie and Bo Wang and Tianyu Fan},
  title = {{Analysis of the Transmission of Project Duration and Cost Impacts Based on the GERT Network Technique}},
  journal = {Symmetry},
  year = {2019},
  doi = {10.3390/sym11030337},
}