Abstract
Generators applying to connect to the U.S. power grid go through an interconnection queue. Most wind and solar generators that begin the process do not complete it. Using new data, we find that a long queue increases the average waiting time, and high interconnection costs are a key factor in a generator's decision to withdraw. We develop and estimate a dynamic model of the queue and quantify the effects of policy reforms. Our simulations indicate that reducing waiting times can significantly increase completions. An alternative queuing mechanism can therefore increase completed capacity by removing certain generators to reduce congestion. A flat entry fee has a similar effect. We also quantify the effects of reforming how interconnection costs are assessed. These policy reforms lead to a substantial reduction in carbon emissions.
Introduction
The transition to a carbon-free power grid in the United States faces a significant, often overlooked hurdle: the interconnection queue. As wind and solar projects proliferate, the backlog of generators waiting to connect to the grid has grown to unprecedented levels. Managed by regional transmission organizations (RTOs), these queues ensure that new capacity does not compromise grid reliability. However, the process has become a major bottleneck, characterized by multi-year delays and high withdrawal rates. This paper provides a rigorous empirical analysis of this "invisible" barrier, quantifying the congestion externalities and evaluating potential policy solutions to streamline the path for green energy.
The Problem: Congestion and Uncertainty
To meet climate goals, the U.S. needs a massive influx of wind and solar power. However, a new generator cannot simply "plug in"; it must join an interconnection queue. The operator conducts a series of engineering studies—Feasibility, System Impact, and Facility studies—to determine if the grid can handle the new load and what upgrades (like new transmission lines) are required.
This process is currently in a state of congestion. It takes years, costs are high and unpredictable, and less than 25% of wind and solar projects that enter the queue actually reach completion. The authors identify a "congestion externality": the presence of one project in the queue slows down the progress of others. This creates a cycle where delays lead to higher waiting costs, prompting developers to withdraw, which in turn changes the cost estimates for remaining projects.
Methodology: A Dynamic Model of the Queue
The authors develop and estimate a dynamic model of the interconnection queue, treating a developer's decision to stay in or leave the queue as an optimal stopping problem.
- Belief Dynamics: In the model, generators form beliefs about when their next study will arrive and what the estimated interconnection cost will be.
- Equilibrium Concept: They introduce a tractable queuing equilibrium that accounts for "non-stationarity"—the fact that the market is changing rapidly as solar costs fall and entry rates skyrocket.
- Two-Step Estimation: First, they model the "production process" of the grid operator (how fast studies are issued). Second, they use observed withdrawal and completion decisions to recover the underlying waiting costs and project payoffs.
Data: Insights from PJM
The study relies on a novel, hand-collected dataset from PJM Interconnection, the largest regional transmission organization in the U.S. (serving 65 million people). The data includes all interconnection requests from 2008 through 2020, totaling 4,085 unique requests and 7,117 detailed engineering studies. Key insights from the data include:
- The Congestion Externality is Real: A 10% increase in the number of projects ahead of a generator reduces its probability of receiving a final study by 5% in a given period.
- Costs are a "Black Box": Interconnection costs have a massive "long tail." While the median cost is $0.05M/MW, the 90th percentile is $0.41M/MW—roughly a quarter of the total installation cost for wind/solar. These costs are nearly impossible to predict using only observable project traits.
- Speculative Entry Clogs the Pipe: Because it is relatively cheap to enter the queue, developers "carpet bomb" the system with requests, hoping one lands in a "cheap" spot on the grid. This speculative behavior creates the very congestion that kills viable projects.
Policy Implications and Results
The research simulates several policy reforms to address queue congestion and maximize completed capacity:
- Speed Matters: Simply delivering studies 10% faster would increase total completed capacity by 4.0 GW (a 5.3% increase).
- Entry Fees Work: Implementing a flat entry fee of $900,000 per project maximizes completed capacity. It screens out small, speculative projects, adding 6.9 GW of total capacity to the grid by reducing congestion for larger, more impactful projects.
- Cluster Studies & Subsidies: PJM’s plan to study projects in "clusters" and share costs proportionally can be highly effective for renewables. If paired with a subsidy, this approach adds more renewable capacity than almost any other reform.
- Climate Benefits: The proposed reforms lead to a substantial reduction in CO2. At a social cost of carbon of $185/ton, the annual benefit is roughly $259 million per GW of added renewable capacity.
Conclusion
The interconnection queue is a critical piece of infrastructure policy. By addressing the congestion externality through better-aligned incentives and streamlined processes, grid operators can significantly accelerate the transition to a cleaner power grid. The findings suggest that managing the queue as a common pool resource—rather than a first-come, first-served line—is essential for meeting national decarbonization goals.
Summary updated