Introduction
The Flexible Job-Shop Scheduling Problem (FJSP) represents a significant logistical challenge in modern manufacturing. Unlike classical job-shop scheduling, FJSP allows operations to be processed on any machine from a set of candidates, requiring simultaneous optimization of both task sequencing and machine assignment. When extended to Multi-Objective FJSP (MOFJSP), the goal shifts to balancing multiple conflicting criteria, such as minimizing makespan (total completion time) and machine workload.
Existing algorithms often suffer from premature convergence or require extensive manual parameter tuning. This paper proposes an adaptive multi-objective evolutionary algorithm (MOEA) that integrates a simplified encoding scheme, a two-stage local search, and autonomous parameter adjustment to address these limitations.
Methodology
The proposed algorithm introduces several key innovations to improve search efficiency and solution quality.
2-Tuple Encoding
To reduce computational complexity, the authors utilize a 2-tuple encoding scheme (Job ID, Machine ID). This simplifies the representation of schedules compared to traditional 3-tuple strings, resulting in shorter chromosomes that are more efficient to process during evolutionary operations.
Two-Stage Local Search (LS)
A critical component of the algorithm is its two-stage local search mechanism:
- LS-I (Pre-evolution): This stage occurs before the main evolutionary process. It uses a left-shift greedy approach to compact the initial schedule, ensuring that individuals start with high-quality "genes."
- LS-II (Polishing): Performed after evolution, this stage focuses on the "critical path"—the sequence of operations that determines the total makespan—to further refine the best-found solutions.
Adaptive Mechanisms
The algorithm employs an Adaptive Crossover Selection strategy, categorizing individuals into "excellent" and "inferior" groups. It applies different operators (IPOX for high-quality parents to refine solutions, and RPOX for lower-quality parents to encourage exploration) based on performance. Furthermore, an Autonomous Parameter Adjustment mechanism dynamically calculates mutation rates based on the job scale and iteration count, significantly reducing the need for manual intervention.
Results and Discussion
The algorithm was evaluated against four standard benchmark sets (Fattahi et al., Brandimarte, Kacem et al., and Dauzère-Pérès).
- Performance: In medium and large-scale instances (MFJS), the proposed algorithm consistently outperformed state-of-the-art models in terms of Pareto dominance and the Inverted Generational Distance (IGD) metric.
- Efficiency: In the MK01-10 benchmarks, it achieved lower makespans than competing models by Bagheri and Xing.
- Simplicity: Notably, the model achieved these results using only three parameters, compared to the 4-13 parameters required by other leading algorithms, making it more practical for industrial deployment.
Conclusion
By combining adaptive evolutionary strategies with a targeted two-stage local search, the proposed algorithm offers a robust and efficient solution for complex scheduling problems. Future work aims to integrate machine learning to enable real-time, data-driven scheduling that can adapt to dynamic factory floor conditions.
Summary updated