Abstract
Conceptual cost is estimated with insufficient information at an early stage of a building construction project, resulting in an inevitable gap between conceptual estimated cost and real constructed cost. For a project to be successful, this gap must be managed to be lower than a reliable level. Therefore, the purpose of this study is to propose a structural process for managing the reliability of conceptual cost estimates at an early stage of a building construction project. In researching this study, conceptual cost estimate experts were interviewed, and a risk management process was studied. Reliability assessment and a review process for improving the quality of conceptual cost estimate and the planning strategy of reliability management based on previous similar projects were added to the present estimate process. The proposed reliability management process will improve the chances of a successful project, by helping to decrease the risk of conceptual estimated cost.
Introduction
In the early stages of building projects, stakeholders rely on conceptual cost estimates to make critical financial and strategic decisions. However, because many project details—such as specific material choices or site conditions—are not yet finalized, these estimates are notoriously prone to inaccuracy. This research addresses the gap between conceptual estimates and actual construction costs by proposing a systematic "Reliability Management Process."
The study defines reliability not as a single perfect figure, but as the probability that the final cost will fall within a predefined, acceptable "error range." The goal is to move beyond simple calculation and create a framework that keeps cost deviations within a predictable threshold.
Methodology
The researchers developed the proposed process through a multi-step qualitative approach:
- Literature Review: Analysis of existing estimation standards (AACE) and risk management frameworks (IPRA).
- Expert Interviews: Qualitative insights from industry professionals to identify real-world pain points.
- Process Integration: Synthesizing findings to insert a "Reliability Assessment" loop and a "Reliability Management Strategy" phase into standard workflows.
- Case-Based Strategy: Using "Key-points"—critical risk factors identified from similar past projects—to monitor and mitigate potential cost overruns.
The Proposed Reliability Management Process
The primary result of this study is the Conceptual Cost Estimate Reliability Management Process. Unlike traditional linear processes, this model introduces a formal feedback loop and strategic risk tracking.
Key Components of the Process:
- Reliability Assessment Step: A formal check to determine if the estimate meets the "acceptable risk level." If reliability is deemed too low, the estimator must identify the factors causing uncertainty and improve the estimate before proceeding.
- Improvement Measures: When reliability is low, the process mandates identifying "weighted" factors that are degrading the estimate's quality.
- Management Strategy Table: A living document that tracks the probability and cost impact of specific risks (e.g., insufficient soil investigation or regulatory changes) and assigns specific response plans and cost buffers to them.
- Benchmarking: A core pillar involves selecting a "most similar project" from historical databases to act as a benchmark for identifying hidden risks that might not be obvious in early documentation.
Conclusion and Future Work
This study provides a structured framework for managing the inherent uncertainty in early-stage construction costs. By integrating reliability assessments and historical project data, stakeholders can significantly reduce financial risk.
However, the authors acknowledge limitations: the framework currently lacks specific automated algorithms for calculating reliability scores, and the assessment of risk probability still relies heavily on expert judgment. Future research should focus on developing computerized systems to store and retrieve historical "Key-points" and creating more objective, data-driven tools for populating management strategy tables.
Summary updated