A multiscale decomposition method for the optimal planning and scheduling of multi-site continuous multiproduct plants

Sebastian Terrazas‐Moreno, Ignacio E. GrossmannChemical 2011

TL;DR

This paper introduces a novel hybrid decomposition method to tackle the computationally challenging problem of simultaneously planning and scheduling production and distribution for multi-site, continuous, multiproduct plants. By combining bi-level decomposition with spatial Lagrangean relaxation, the authors demonstrate a significant speedup in solving large-scale problems compared to traditional full-space or pure bi-level approaches.

What Problem Does This Paper Address?

The chemical industry faces a complex optimization challenge: integrating production planning (medium to long-term decisions about what and how much to produce) with production scheduling (short-term decisions about the exact timing and sequence of operations). This problem becomes even more intricate when dealing with multi-site, multi-market networks, as it involves different temporal scales (weeks/months for planning, days/hours for scheduling) and spatial scales (individual production units to geographically distributed networks). Solving this simultaneously is computationally intractable due to its NP-hard nature. Existing methods often struggle with the scale and complexity, leading to long solution times or suboptimal decisions. This paper aims to develop a more efficient and scalable approach to find optimal or near-optimal solutions for these integrated planning and scheduling problems.

Methods

The authors propose two decomposition methods:

  1. Bi-level Decomposition: This method extends an existing bi-level decomposition strategy to a multi-site, multi-market setting. It decomposes the problem into an upper-level planning problem and a lower-level scheduling problem. The upper level uses an aggregate sequencing model (akin to a Traveling Salesman Problem) to account for sequence-dependent transitions, while the lower level uses the planning solution to limit its search space. Integer cuts are used to tighten the upper-level problem.
  2. Hybrid Bi-level Lagrangean Decomposition: This is the novel contribution. It builds upon the bi-level decomposition but further relaxes the upper-level problem using spatial Lagrangean relaxation. This effectively decomposes the problem by site and market, allowing for parallel solving of subproblems. The Lagrange multipliers are initialized using dual variables from a linear relaxation, which are shown to approximate equilibrium transfer prices.

Datasets

Not discussed in the paper. The paper presents four case studies with data provided in tables and figures.

Key Insights and Ideas

  • Decomposition is Crucial for Scale: For large-scale planning and scheduling problems, decomposition methods are essential to achieve solutions within reasonable computational time, outperforming full-space solutions.
  • Hybrid Approach Offers Speedup: The proposed hybrid bi-level Lagrangean decomposition method demonstrates a significant computational advantage over pure bi-level decomposition, especially as problem size grows.
  • Lagrange Multipliers as Transfer Prices: The Lagrange multipliers in the hybrid method are shown to be close to equilibrium transfer prices between production sites and markets, providing economic interpretability.
  • Upper-Level Bottleneck: The upper-level planning problem is identified as the bottleneck in bi-level decomposition. Relaxing it in the hybrid method is key to its efficiency.
  • Heuristic Lower Bound: Fixing the product assignments from the upper level into the lower level provides an effective heuristic lower bound for the overall problem.

Key Results

  • Example 1 (Small Scale): The full-space model solved in ~4 CPU seconds. The bi-level decomposition converged in less than one CPU second, yielding the same optimal profit and schedule. The hybrid bi-level Lagrangean algorithm took 10 seconds to converge within a 2% tolerance.
  • Examples 2, 3, and 4 (Larger Scale):
    • Example 2: Bi-level and hybrid algorithms had similar computational times (9 CPU s), significantly faster than the full-space model (60 CPU s).
  • Example 3: The hybrid algorithm was substantially faster (751 CPU s) than the bi-level decomposition (4,939 CPU s) and orders of magnitude faster than the full-space model (10,000 CPU s).
  • Example 4: The full-space model could not be solved due to memory limitations. The hybrid algorithm solved it in 1,106 CPU s, while the bi-level decomposition took 7,638 CPU s.
  • General Trend: As problem size increases, the hybrid algorithm's computational advantage over bi-level decomposition becomes more pronounced.

Limitations and Future Work

  • Integer Cuts in Hybrid: The paper notes that integer cuts, effective in pure bi-level decomposition, are not directly applicable in the hybrid method due to the changing objective function coefficients from Lagrange multipliers. This limits the tightness of the upper bound in the hybrid approach.
  • Convergence Tolerance: The hybrid algorithm converges within a 2% optimality tolerance. Achieving 0% tolerance is unlikely due to the duality gap.
  • Future Work: The authors suggest that the efficiency of the hybrid method makes it suitable for very large industrial problems. Further research could explore ways to improve the tightness of the bounds or explore other decomposition strategies. The paper also mentions that the model does not consider start-up times for plants, which could be an area for future extension.

Summary updated

BibTeX
@inproceedings{terrazasmoreno2011multiscale,
  author = {Sebastian Terrazas‐Moreno and Ignacio E. Grossmann},
  title = {{A multiscale decomposition method for the optimal planning and scheduling of multi-site continuous multiproduct plants}},
  booktitle = {Chemical},
  year = {2011},
  doi = {10.1016/j.ces.2011.03.017},
}