Abstract
Power transmission and transformation project construction is an important guarantee of the safe and stable supply of energy power. As unified markets deepen, project cost components face multiple influences and dynamic evolution. Enhancing the "toughness" and "elasticity" of cost management is essential for the precision and dynamic control requirements of power grid enterprises. This paper proposes a stimulus transmission analysis technology based on the DEMATEL method to visually express the relationships between internal factors. By exploring how market factor changes influence project costs, this research provides a reference for improving the efficiency and quality of cost control in power transmission and transformation projects.
Introduction
Power transmission and transformation projects represent massive capital investments critical for energy stability. However, their cost structures are notoriously complex and sensitive to the deepening development of a unified large market. While engineers generally understand that material prices or labor costs affect the bottom line, the interrelationships between these factors are often treated as a "black box." For instance, how does a shift in the Purchasing Managers' Index (PMI) ripple through to land prices or miscellaneous expenses? This paper seeks to understand the stimulus and conduction—the cause-and-effect pathways—that allow market volatility to penetrate project budgets.
Methodology
The research utilizes a hybrid approach combining qualitative expert insight with quantitative matrix analysis via the Delphi and DEMATEL methods.
The Delphi Method
To populate the initial data, researchers consulted 20 experts to evaluate the direct relationships between 10 key factors, ranging from macroeconomic indicators like GDP and CPI to specific project costs like manual unit prices.
DEMATEL Method
The Decision Making Trial and Evaluation Laboratory (DEMATEL) method serves as the core analytical engine. It involves constructing a Direct Influence Matrix, normalizing it into a Comprehensive Influence Matrix, and calculating four key metrics:
- Influence Degree (D): How much a factor affects others.
- Affected Degree (C): How much a factor is affected by others.
- Centrality (D+C): The factor's total prominence in the system.
- Cause Degree (D-C): Whether a factor is a net "driver" (positive) or a net "result" (negative).
Results and Discussion
Macro Drivers and Result Factors
The analysis reveals a clear hierarchy of influence. Macroeconomic indicators—specifically CPI (Consumer Price Index), PMI, and GDP—occupy the first quadrant of the centrality-cause diagram. These factors exhibit high centrality and high cause degrees, identifying them as the primary "stimulators" of the system.
Conversely, factors like "Main cost" and "Miscellaneous expenses" have the highest Affected Degrees and negative Cause Degrees. They are the ultimate recipients of market ripple effects but exert almost no influence back on the market factors. The Producer Price Index (PPI) acts as a critical bridge, significantly influencing material and mechanical unit prices and linking the broad economy to specific construction costs.
Quantitative Impact Mapping
The study provides a quantitative ranking of market influence:
- Top Driver: CPI had the highest Cause Degree (1.482), identifying it as the strongest independent variable.
- Most Influential Macro Factors: GDP and CPI showed the highest centrality (both above 1.7), marking them as the most critical nodes in the cost network.
- Most Affected: "Main cost" had an Affected Degree of 2.517, the highest in the study.
The Comprehensive Impact Diagram visualizes the magnitude of influence between elements, providing a "road map" for cost controllers to anticipate where a market shock will likely hit next. Substation project costs and electricity construction costs were found to be the most sensitive areas.
Conclusion
While the model identifies the structure of influence, it relies on expert consultation which can introduce subjective bias. Future work should focus on establishing dynamic monitoring mechanisms. Rather than relying on static cost estimation, power grid enterprises should implement real-time tracking of high-cause factors (like CPI and PPI) to create proactive, elastic project management strategies that can adjust as market stimulus occurs.