Abstract
Overhanging pavement slabs on the defected subgrade are mainly caused by flood erosion that partially hollows out the subgrade, which leaves the highway in an unstable condition. This paper develops a kind of emergency repair technology of suspended road slab anchor pulling technology for this type of disaster, combining the working principle of self-anchored emergency anchors with its components, calculating the road slab through the equivalent method of concrete road slab combined with structural mechanics, analyzing the stability of this emergency repair technology, proving that this kind of emergency repair technology can be applied in the actual situation of the emergency, enriching China's repair methods of water damage to the roadbed, and meeting the strategic needs of the transportation construction.
Introduction
Extreme flood events often erode the subgrade—the foundation of earth and stone beneath asphalt or concrete—leaving pavement slabs precariously overhanging. These sections are extremely dangerous and typically lead to total road closures. Traditional repair methods, such as backfilling and compacting, are time-consuming and often unfeasible while floodwaters are still receding or when heavy equipment cannot reach the site. This research addresses the need for a "race against time" solution to restore emergency access for pedestrians and light vehicles immediately following a disaster.
The Suspended Road Slab Anchor Pulling System
The authors propose a suspended road slab anchor pulling technology that functions as a hybrid between a road and a suspension bridge. The system is designed for cases where the subgrade defect width is less than one-half of the total subgrade width, ensuring enough undamaged foundation exists to act as a fulcrum.
Key components include:
- Self-Anchored Bolts: High-strength bolts drilled into the stable "cliff wall" or inner slope of the highway.
- Steel Ropes & Support Piers: Steel strands connect these anchors to the outer edge of the overhanging slab, with precast concrete piers (abutments) placed on the slab to redirect tension.
This system can be fully installed and functional within 5 to 8 hours, providing a significant improvement over traditional reconstruction timelines.
Structural Modeling and Mechanical Analysis
To validate the safety of the repair, the overhanging slab is modeled as a statically determinate structure. The authors utilize the "equivalent method of concrete road slabs" combined with classical structural mechanics to calculate internal forces and bending moments at various points of the slab.
By decomposing the forces, specific formulas are derived to calculate the necessary tension (F) in the steel ropes and determine the required number of steel strands (n) based on a safety factor (η). This framework allows field engineers to quickly determine safety limits on-site.
Key Results and Case Study
The technology was validated using data from a real-world scenario in Youxi County, Fuzhou City, where heavy rains frequently cause subgrade washouts. The analysis demonstrated:
- Load Capacity: The design supports a bearing capacity of 50kN per linear meter, sufficient for pedestrians, small vehicles, and flat semi-trailers.
- Case Success: For a 2m suspended section on a 4.5m wide lane, calculations showed that a single 15.2mm steel strand per pier was sufficient (calculated n approx 0.38).
- Stability: The system successfully stabilizes the slab against the weight of the concrete and the dynamic loads of vehicle travel.
Limitations and Future Work
While effective for rapid response, this technology is strictly an emergency repair. It relies on the stability of the inner slope to hold the self-anchored bolts; in areas with widespread landslides or extremely soft soil, the method may be inapplicable. Future research could focus on automating the tensioning process or adapting the method for wider road washouts, further enriching emergency repair strategies for highway infrastructure.