GERT Network of Cost and Risk Control of Construction Project

Yan Xue, Ding Liu, Xu LuoOpenalex Unknown 2022 · OpenAlex

Abstract

The early stage of project investment is the most optimal period for preventing project budget overruns, but the basis for evaluating the pre-project investment decision and risk management implementation strategy is unclear. This paper fills the research gap of quantitative analysis of cost risks, and precise matching of risk control strategies in the field of whole-process engineering cost management thus providing an innovative solution method for intelligent matching risk control activities and project cost overruns forecasting. Graphic Evaluation and Review Technique (GERT) and Bayesian updating method were combined to develop an uncertain system analysis model of the project construction process, and Monte Carlo simulation was applied to figure out the analytical solution with different risk control methods in the project construction period. The results showed the risk transfer probability expectation and cost expectation results while adopting the optimal matching of risk control strategy in the optimal phase of the project construction process can weigh whether the risk control measures are worth implementing under the condition of limited construction period and resources combining with the risk threshold of investors.

Introduction

Construction projects are notorious for budget overruns. Whether it’s a high-speed railway or a skyscraper, costs often spiral out of control as soon as physical work begins. This research introduces a sophisticated mathematical framework designed to shift project management from reactive "firefighting" to proactive precision.

In civil engineering, the "Ability to Influence Cost" curve highlights a stark reality: the power to save money is highest during the decision-making phase but drops significantly once construction starts. Despite this, many project managers lack quantitative methods to match specific risk control strategies—such as strengthening technical reviews or improving material quality control—to specific project stages. Current methods often treat risk as a static buffer. This paper addresses this gap by treating construction as a dynamic, uncertain system where risks evolve and transfer between stages.

Methodology: GERT and Bayesian Updating

The proposed framework utilizes a three-pronged mathematical approach to model and mitigate cost overruns:

  1. GERT (Graphical Evaluation and Review Technique) Networks: Unlike traditional linear project management tools, GERT allows for probabilistic nodes and feedback loops. This is essential for construction, where failed inspections or design revisions can send a project back to earlier stages.
  2. Bayesian Updating: The model treats risk control implementation as a "prior" that is updated. For instance, enhancing budget estimate accuracy adjusts the probability of overruns in subsequent stages based on that specific action.
  3. Monte Carlo Simulation: To identify optimal strategies, researchers ran 2,000 simulations, testing combinations of risk control strategies across nine project nodes to minimize the balance of risk probability and cost.
The GERT network model for construction project risk analysis, featuring probabilistic nodes and feedback loops.

Case Study: Fortune Plaza, Qingdao

The model was validated using the Fortune Plaza project in Qingdao, China. This commercial office building, featuring a frame structure, had a substantial budget of approximately 1.48 billion CNY (~$233 million USD).

Key parameters and budget details for the Fortune Plaza project in Qingdao, used for model validation.

The researchers used historical engineering data to define parameters such as transfer probability, mean cost, and standard deviation for the simulation.

Key Insights and Results

The framework explicitly accounts for "self-loops"—revisions and reconstructions—that are often missed by traditional models. By viewing risk as a dynamic "transfer probability" that flows from design to construction, the model provides a more realistic representation of project dynamics.

Key findings from the case study include:

  • Predictive Accuracy: The framework achieved an 81.4% accuracy rate in predicting cost overruns compared to actual outcomes.
  • Cost Mitigation: Without risk control, the predicted overrun was 43.4%. Implementing the optimal strategies identified by the simulation reduced this to just 8.37%.
  • Strategic Optimization: The simulation identified specific winning strategies for different nodes. For example, the "Engineering Design" stage required a simultaneous adoption of multiple control techniques due to its high impact and complexity.

Conclusion

While the model significantly advances cost control, it remains dependent on the quality of initial data. Future work aims to establish larger industry-wide databases to refine intelligent matching and expand the model to include the entire life cycle, including maintenance and operation costs. This research provides a practical tool for pre-project investment decision-making and precise risk management during construction.

Summary updated

Abstract

The early stage of project investment is the most optimal period for preventing project budget overruns, but the basis for evaluating the pre-project investment decision and risk management implementation strategy is unclear. This paper fills the research gap of quantitative analysis of cost risks, and precise matching of risk control strategies in the field of whole-process engineering cost management thus providing an innovative solution method for intelligent matching risk control activities and project cost overruns forecasting. Graphic Evaluation and Review Technique and Bayesian updating method were combined to develop an uncertain system analysis model of the project construction process, and Monte Carlo simulation was applied to figure out the analytical solution with different risk control methods in the project construction period. The results showed the risk transfer probability expectation and cost expectation results while adopting the optimal matching of risk control strategy in the optimal phase of the project construction process can weigh whether the risk control measures are worth implementing under the condition of limited construction period and resources combining with the risk threshold of investors. This is of practical significance for the pre-project investment decision and precise implementation of risk control during the construction process.
BibTeX
@inproceedings{xue2022gert,
  author = {Yan Xue and Ding Liu and Xu Luo},
  title = {{GERT Network of Cost and Risk Control of Construction Project}},
  booktitle = {Openalex Unknown},
  year = {2022},
  doi = {10.2991/978-94-6463-038-1\_61},
}
Figure